Adani Energy Secures Bihar Transmission Contract Until 2028
Adani Energy Solutions Wins ₹500 Crore Bihar Transmission Project to Carry Power From Pirpainti Plant
The project will connect the upcoming 2,400 MW thermal power station to Bihar’s electricity network. It will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity, with completion scheduled for the fourth quarter of 2028.
Adani Energy Solutions Limited (AESL) has secured a power transmission project in Bihar to carry electricity from the upcoming 2,400 MW Pirpainti thermal power plant. The project is expected to earn an annual tariff of around ₹500 crore after commissioning and will add a major transmission network to the company’s operations.
Announced on 19 November 2026, the project has been awarded through the Tariff Based Competitive Bidding (TBCB) mechanism. AESL will execute it through a special purpose vehicle (SPV), Vikramshila Power Transmission Limited. The company has set the fourth quarter of 2028 as the target for completion.
The electricity will come from Adani Power’s proposed 3X800 MW Ultra Super Critical Thermal Power Plant at Pirpainti in Bhagalpur district. Its three generating units will have a combined capacity of 2,400 MW.
The new transmission system will carry electricity from the plant towards Jhanjharpur, Begusarai, Bethauli and Bakhtiyarpur. It will also connect with existing transmission infrastructure in Bihar, helping the state move electricity to areas where it is needed.
The proposed transmission system will include four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli and Begusarai. GIS technology uses insulated equipment to control and distribute electricity within a substation. It can help reduce the space needed for electrical installations, which is useful where land availability is limited.
The project will include three 400 kV Double Circuit Double String (DCDS) transmission lines: Pirpainti-Jhanjharpur, Pirpainti-Begusarai and Begusarai-Bakhtiyarpur.
Two additional 220 kV DCDS lines will connect Jhanjharpur with Bethauli and Begusarai with Begusarai Town.
The work also covers the Line-In Line-Out (LILO) connection of existing 220 kV and 132 kV transmission lines at Jhanjharpur. AESL will construct 400 kV line bays at Bakhtiyarpur Grid Substation (GSS).
These connections will allow electricity generated at Pirpainti to enter the wider state network. The high-voltage lines will carry power over long distances, while substations will help manage voltage levels and transfer electricity between different parts of the grid.
The transmission project is closely linked to the construction of Adani Power’s Pirpainti Ultra Super Critical Thermal Power Plant.
According to the Central Electricity Authority’s (CEA) September 2026 report, the plant is being developed at Srimadpur and Harinkol villages in Pirpainti, Bhagalpur district. Larsen & Toubro (L&T) is listed as the main plant equipment supplier.
The three units have a capacity of 800 MW each. The CEA report gives June 2029 as the expected trial-run date for the first unit, December 2029 for the second and June 2030 for the third.
The plant will use coal and light diesel oil (LDO). Its estimated project cost is ₹28,851 crore. The report records total expenditure of ₹1,650 crore up to 30 September 2026.
Power Purchase Agreements (PPAs) have been signed with Bihar’s distribution companies. The CEA report also records coal allocation of 10.43 million tonnes per year from Eastern Coalfields Limited (ECL) under the Shakti B(iv) policy.
The planned transmission completion date of late 2028 comes ahead of the expected trial runs of the three generating units. This gives the transmission project a separate construction schedule that must be coordinated with the power station’s progress. Any delay in either part could affect the movement of electricity once the plant begins producing power.
The Bihar project comes as India prepares for a major expansion of its electricity network. The Ministry of Power’s National Electricity Plan (Transmission), notified in 2024, sets out the infrastructure requirements for the period from 2023 to 2032.
According to the Ministry’s July 2026 update, India’s peak electricity demand is projected to reach 388 GW by 2032. The country’s transmission network is expected to grow from 5.09 lakh circuit kilometres in June 2026 to 6.48 lakh circuit kilometres by 2032.
The transformation capacity of substations is also expected to increase from 1,478 GVA to 2,345 GVA during the same period. The government has identified growing demand from electric vehicles, data centres and industrial activity as factors behind the need for additional power infrastructure.
India added 35,172 circuit kilometres of transmission lines and 270,174 MVA of transformation capacity at 220 kV and above during the three financial years from 2023-24 to 2025-26.
These figures explain why new transmission projects are being planned alongside power generation facilities. A power station needs suitable lines and substations to send electricity to homes, businesses and factories. Without sufficient transmission capacity, additional generation cannot be fully used by the electricity network.
The Pirpainti contract will increase the size of Adani Energy Solutions’ transmission business. Once the new infrastructure is completed, the company expects its transmission network to reach 30,683 circuit kilometres, compared with its existing 29,802 circuit kilometres as of 30 September 2026.
Its transformation capacity will rise from 143,425 MVA to 146,585 MVA after the addition of 3,160 MVA.
AESL has also put its transmission capital expenditure at approximately ₹91,500 crore following the latest project win. This figure relates to its transmission investment programme and should not be confused with the annual tariff of around ₹500 crore expected from the Pirpainti project after commissioning.
The company had secured the Vizag and Satara transmission projects earlier in 2026. According to its November 2026 business update, those projects together added around 2,000 circuit kilometres to its transmission portfolio.
AESL operates in electricity transmission, distribution and smart metering. Its distribution operations serve consumers in Mumbai and the Mundra Special Economic Zone.
Commenting on the Bihar project, Kandarp Patel, CEO of Adani Energy Solutions, said:
“The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone. It will enhance grid reliability and resilience and help the state meet its growing power demand. We remain committed to building reliable and efficient transmission infrastructure that supports the country’s long-term energy security.”
The success of the project will depend on the timely construction of its transmission lines, substations and connections with the existing network. Its completion will also need to match the progress of the Pirpainti generating station.
For Bihar, the project will add another major link between electricity generation and the state transmission system. The planned completion in late 2028 will mark an important stage in preparing the network for the 2,400 MW power station, whose three units are scheduled to begin trial runs between 2029 and 2030.