Delhi High Court Orders SAP to Continue Support for Nayara Energy
Delhi High Court Directs SAP to Continue Services to Nayara Energy, Refuses Interim Relief
A two-judge bench of the Delhi High Court has refused to give SAP any interim relief against an earlier order directing it to restore software support services to Nayara Energy.
While issuing a notice on SAP’s appeal, the bench of Justice Prathiba M. Singh and Justice Dinesh Bhatt clearly directed SAP to continue providing services to Nayara Energy as ordered by the single judge.
In its order dated 5 November, the two-judge bench had orally observed that “The SAP system may be considered an essential service for the operation of Nayara’s refinery. It is also not practical for the company to replace its entire IT system immediately.”
In September, a single-judge bench of the Delhi High Court, led by Justice Vikas Mahajan, had directed SAP to immediately restore key support services to Nayara Energy.
In its petition, Nayara Energy, which meets around 8% of India’s fuel needs, argued that stopping SAP’s support services had put its key IT systems at risk. The company said this could lead to system failures, cybersecurity threats and problems in its operations.
Nayara Energy told the court that moving to another ERP platform could take several years and cost hundreds of crores of rupees. It said continued support from SAP was necessary to keep its business running smoothly and meet regulatory requirements.
In his 120-page order, Justice Mahajan said that stopping SAP’s support services could put Nayara Energy’s key software systems at risk of system failures, cyber security breaches and problems in daily operations. The court stressed that “A continuous flow of technical support services is very important for infrastructure of this level.”
The latest development is in Nayara Energy’s favour, as the court has directed SAP to continue its key software support services despite SAP’s appeal. Until the appeal is finally decided, this order will help protect the company’s main business software systems and keep its operations running.
The next hearing in the case is scheduled for 11 January 2027.